- Home
- Government
- Departments
- Public Works
- Construction Projects
ROAD CONSTRUCTION AND INFRASTRUCTURE PROJECTS
The Town of Bow has many construction and infrastructure projects both underway and in the planning stages. We would like to keep you informed as to the status of these projects. We will continually update this page as these projects progress, as well as post updates on the Town of Bow Facebook page.
If you have any questions on any construction going on around Town, we encourage you to call our Department of Public Works Department at 223-3940, or the Town Manager's Office at 223-3910.
Page Road Bridge Replacement Project
This project includes the total removal of the existing metal pipe arch bridge and concrete headwalls and replacing it with a new precast concrete arch bridge, headwalls and wingwalls., drainage, and approach road work and paving. The cost of the project is $1,387,500. The Town is paying 20% of the project cost and the State of NH State Bridge Aid program will be covering 80%. Funding for the Town's share was approved at the 2023 Town Meeting.
A contract has been awarded to WP Davis Construction for the work. Dubois & King designed the new bridge and The Turner Group will be providing project oversight.
Work on the project began on July 14, 2025 and the project is scheduled for completion at the end of October 2025. A traffic detour with ample signage has been put in place and it will stay in effect until the end of October 2025.
White Rock Hill Rd./Falcon Way Intersection Improvements Project (Completed)
This project included the construction of a new turning lane on Falcon Way and pedestrian safety improvements. The contractor was Michelle Baillargeon Construction Services and Northpoint Engineering provided the plans and project oversight. Funding for the project was approved at the 2024 Town Meeting. Work on the project began on June 16, 2025 and completed on August 22, 2025.
Annual Town Road Paving Projects - 2025
The Town has approximately 100 miles of roadway and our annual paving plan calls for the rehab and paving of approximately 4 miles of roadway each year. Before a road is paved, the DPW crew installs or replaces catch basins and culverts and sub-surface drainage. A contractor is then hired to reclaim and pave the road. DPW then adds a gravel shoulder to each newly paved section.
2025 list of roads and status as of 9/15/25:
- Ryan Road - 0.32 Miles, 1,700 ft. - 1,600 tons - 2.25-inch overlay - Completed
- Rosewood Drive - 0.587 Miles, 3,100 ft. – 950 tons - Completed
- Dean Avenue. - 0.487 Miles, 2,600 ft - 750 Tons - Completed
- Erin Drive - 0.528 Miles, 2,800 ft - 400 Tons - 1 inch overlay - Completed
- Heidi Lane - 1.104 Miles, 6,000 ft - 1800 Tons - Paving date - Week of October 13
- Nancy Drive - 0.198 Miles, 1,050 ft - 300 Tons - Paving date - October 10
- Betty Lane - 0.331 Miles, 1,800 ft - 510 tons - Paving date - Week of October 13
- Poor Richards Drive - 0.572 Miles, 3,025 ft. - 920 tons - Paving date - Week of October 13
Town Water System Expansion to Bow Junction and Bow Mills
A study was conducted by the Town's engineering firm, Dubois & King in FY2019-20 to develop options to provide municipal water to Bow Junction and Bow Mills. The study was funded by the State through its MBTE mitigation fund. The Board of Selectmen reviewed the study and authorized D&K to perform design work on extending the existing water main from Vaughn Road, north on Route 3A, to Bow Junction and Bow Mills.
(8/20/25) The Town has been informed by NH DES that the project has been ranked #3 based upon the pre-application that was submitted to the State. Funding would include a grant for a portion of the project and low interest loans for the balance of the cost.
(8/27/25) The Town has been awarded a $1,500,000 grant and access to $2,110,203 in low interest revolving fund loans for the project.
South Bow-Hooksett Water System Interconnection
A feasibility study was conducted by Dubois & King to explore expanding the Bow water system to serve the South Bow TIF District and to extend the system to the Hooksett Village Water District system.
(6/17/25) Town representatives have met with representatives from the Hooksett Village Water Precinct and a project plan is being formulated. The Board of Selectmen has approved a contract with Dubois & King to design the water extension and provide an updated opinion of cost.
(8/20/25) Dubois & King has formulated an initial layout of the proposed waterline from River Road to the existing HVWP main in front of Sullivan Tire. They will be meeting with representatives from the Town, WhiteWater and NH DOT to review the drawing and then walk any portions of the alignment where the group may have any questions or concerns.
Pending
River Road Bridge Replacement Project
This project is to replace the bridge located near Vaughn Road. Design work has also been completed by Dubois & King. The current estimated cost of the project is $1,313,383. The Town will pay 20% of the project cost and the State of NH Bridge Aid program will cover 80%. Funding for the project was approved at the 2024 Town Meeting.
(6/17/25) The final project design is currently under review by NH DOT. The project is tentatively scheduled to be advertised for bids in February 2026 with construction beginning in Spring 2026.
Route 3A Corridor Safety Improvement Project
The NH Department of Transportation (NH DOT) is moving forward with two intersection improvement projects at the River Road/Route 3A intersection and the Grandview Road/Route 3A intersection. Funding for the project is within the NH Ten Year Transportation Improvement Plan 2017-2026.
NH DOT engineers have met with Town officials to approve the new layouts and design work on these projects is underway. The cost of both projects will be fully funded by the State of New Hampshire.
-
Public Works Department
Physical Address
12 Robinson Road
Bow, NH
Mailing Address
10 Grandview Road
Bow, NH 03304
Phone: 603-223-3930Fax: 603-228-2209
Shop Phone: 603-223-3938
Hours
Monday - Friday
6 a.m. - 2:30 p.m.
-
Timothy Sweeney
Director of Public WorksPhone: 603-223-3930
-
Rick Wombolt
Fleet ManagerPhone: 603-223-3938
-
Lois Richards
Administrative AssistantPhone: 603-223-3930